Preparing for a DAR's Conformity Inspection
There are two types of conformity inspections, parts conformity and installation conformity.
Part (s) conformity DAR will review all design data and production records used to build the parts and assemblies and any inspection (s) to verify part (s) meet the design criteria.
Installation conformity DAR will review all design data and production records used to install the part (s) and assembly (ies) on an aircraft and any inspection (s) to verify installation (s) meet the design criteria..
In both cases, the parts and assemblies and the installation of those same parts and assemblies must be in 100% conformance with the design data. No deviations from the design data are permitted, nor are any Material Review Board action(s) allowed.
**NOTE: The conformity for any given part must be completed prior to it being installed on or in the aircraft.
A DAR's conformity inspection involves the review of all design data and production documents that are generated as part of the manufactures design approval program with the Federal Aviation Administration (FAA). Also, the manufacturer will also have to have full traceability of all parts used in the article/installation.
The DAR will need the following signed forms before starting the conformity inspection:
¹ NOTE: If your company is not the program applicant with the FAA, the DAR will need a letter authorizing you to act as an agent on their behalf. This letter must be signed by the program applicant. Please note that the inspection cannot begin until the DAR has received authorization to do so in the form of the above referenced documents.
² NOTE: A conformity inspection is not to be used in place of a final inspection. By the time the conformity inspection takes place, the applicant should have performed all necessary tests and inspections and found 100% conformance to the design data. The DAR will perform no tests or measurements themselves; rather they will examine all production records and request that certain random inspections be conducted again as a spot check to verify that the parts, assemblies, and installations are in compliance with the design data. The DAR does not perform the responsibilities of the applicant; they verify that the applicant has performed their responsibilities.
The required forms for any given inspection are listed on the Request for Conformity and the original signed documents are sent to the program office. Except for the Original FAA Form 8130-3(s) which must remain attached to the part and/or assembly, a copy of the 8130-3 will be sent to the program office.